Priority Items
( still require funding and labor )
to get Permit for Occupancy of Bottom Floor
| 1.Sanctuary Doors to be hung ( Donated)
need Labor 2. Carpet to be laid ( $ 5600 ) written estimate 3. Baptistery Lid to be Fabricated ( $600 ) plus Labor 4.Exterior Doors to be Finished and hung (Labor) 5. .Land filler Dirtwork ( $3500) 6. Sidewalk reconstruction no estimate 7. Relocating A/C intake and Thermostat (no estimate) 8. Cabinets in Fellowship Hall (no estimate) 9. Handrail for stairwell (no estimate) 10.Upstair Doors (donated) Labor to hang |